Hi everyone! ![]()
I’m looking for advice and best practices for setting up a capacity planning and workload tracking system in monday.com for a consulting firm with a multi-project staffing model.
About our environment:
-
~30 consultants
-
Each consultant can be assigned to 8–12 projects at a time
-
Each project typically has 4–6 consultants assigned
-
We need to plan and track work by week and in hours
Key requirements:
We need visibility into:
-
Hours by person
-
Hours by project
-
Hours by role (Consultant, Senior Consultant, PM, Director)
-
Weekly capacity utilization
We also need to track:
-
Sold/confirmed work vs Proposed/pipeline work
-
Planned hours vs Actual hours
-
Remaining hours when actuals differ from plan (ex: planned 10, worked 7)
Functional goals:
-
Easy to adjust weekly assigned hours
-
Minimal administrative overhead
-
Avoid duplicate data
-
Works well with the Workload widget and dashboards
-
Scalable and simple to maintain
-
Supports reallocation when plans change
What I’m trying to design:
A structure that likely includes:
-
A Projects board
-
A People/Capacity board
-
An Assignments board (one person + one project + one week)
-
Dashboards for workload and utilization
-
Automations for alerts (overcapacity, actuals exceeding plan, etc.)
Before I build this, I’d love to hear from anyone who has:
-
Implemented capacity planning for consulting or agency-style teams
-
Successfully used the Workload widget for multi-project staffing
-
Tips on board structure, formulas, or automations
-
Lessons learned (what to avoid, what worked well)
If you have screenshots, examples, or templates you’re willing to share, that would be incredibly helpful.
Thanks in advance — really appreciate this community’s expertise! ![]()