hi helpful Monday folks.
I am learning monday projects and portfolios
I am learning monday baselines after already learning gantt charts.
I have been able to create a baseline off my gantt chart which in turn automatically creates the Project Baseline and Difference columns on my project.
In my timeline column i am not enabling weekends.
When i delay my timeline start date by a week the difference calculation is 7 days.
ok from a math perspective this makes sense but from an accountability perspective the action is only 5 days late.
Is there a do not include weekends on this out of box difference functionality similar to the timeline? Is there a fancy formula to edit the existing formula to exclude weekends?
thanks in advance