Gantt baseline Difference calculation

hi helpful Monday folks.

I am learning monday projects and portfolios

I am learning monday baselines after already learning gantt charts.

I have been able to create a baseline off my gantt chart which in turn automatically creates the Project Baseline and Difference columns on my project.

In my timeline column i am not enabling weekends.

When i delay my timeline start date by a week the difference calculation is 7 days.

ok from a math perspective this makes sense but from an accountability perspective the action is only 5 days late.

Is there a do not include weekends on this out of box difference functionality similar to the timeline? Is there a fancy formula to edit the existing formula to exclude weekends?

thanks in advance