Subitem dependency

I’ve looked at the FAQ and don’t see my question. I have attempted to set up dependency on sub-tasks/subitems but they aren’t working. What I did was make sure each Main task had a subtask and then I set the dependency from main task 1/subtask to main task2 subtask1. I set up the timeline not to start until other finished so I can auto update my subitem dates. But when I test (change the subtask in main 1 to a week later) my main task 2 subitem 1 stays the same.

2 Likes

I’m looking for the same function for subitems and noticed that nothing has changed for a month around this. Can someone from Monday give us an update on this?

Edit: I noticed in the subitem feature release schedule there is no mention of subitem dependencies (unless I’m missing it). However, this is a critical need for subitems to be at all useful within project plans…

1 Like

I agree, these dependencies would be very very useful o use on subitems

I certainly like the subitems function, but unless I am mistaken it seems that subitems can only be dependent on other subitems, and not main items. Similarly items can only be dependent on other main items, but not on subitems… This certainly limits the functionality of subitems! Another thing I miss regarding subitems is that there is an automation which says," when the status of an item changes to … change the status of its dependency to … However this automation doesn’t exist in subitems and the custom automation maker doesn’t have it either!

Hey @fwoodley, @randi1, @Jefes, and @jpinbe! Thanks for posting and for your feedback on dependencies in subitems.

This is something we’re planning on releasing after we release crossboard dependencies. Crossboard dependencies are on the roadmap for Q1 of 2021, so I would guess that the subitem dependencies will be out in Q1 or Q2.

If you have any questions in the meantime or want us to help you brainstorm workarounds for this feature, feel free to write in to support@monday.com to let us know :blush:

1 Like