Hi All!
I really need some help!
We are working with Monday Dev setting our projects and we ussually use the Strict dependencies.
We notice today that when setting a dependencie linked to a timeline and duration column, the dates on the timeline colum does not reflect the dates are are related to de dependencie and it leaving a lag
and the dates that are shown in the timeline starts with today’s date.
For example:
Sprint 1 depends on Sprint 0, in theory, Sprint 1 should start on Oct 13th but Monday is showing this:
This is happening for all boards and groups we have