I’m setting up workflows that build standard deliverables.
A simple proofing task might have the following steps:
Proofing Group
- Proofing Item
- Receive content (7 days)
- Estimate delivery (1 day)
- Proof and deliver (3 days)
- Requested Delivery Date (n/a)
I can set up a workflow that has sub-item timelines with a specific date or using the “Today” value.
Is there a way to set up relative timelines within the workflow block settings? (“Today”+x days)
I think I can create formula columns that would allow for it:
Date Item Created || Date plus 7 days || Date plus 8 days || Date plus 11 days
But I’d like to avoid adding that many columns for a one-time setup.