Hi there
Struggling with this one…
We use Timeline + Numeric Combo (Project duration + Duration) Column to feed a gant chart for scheduling purposes and it works great. what id like to do now is in a chart view is have the ability to sort the amount of duration days per technician that appear within in a certain window of time example January of 2026 only. What im finding is when you filter by Timeline(project duration) there is no ability to filter by “between 2 dates”. does anyone have a work around for this?
Cheers
ACECS