Good day! Been a while since I had the ability to work in this platform, glad to be back!
I wanted to reach out here to, hopefully, get some ideas or assistance on what I am trying to accomplish. I’ll try not to be too long winded.
I have built and automated a Project Management set of boards. The high level ‘Projects’ and the low-level ‘Tasks’. Each of the tasks has a set of 13 sub-tasks that make up the project, each with their own durations. I have everything flowing the way I would like, for the most part, however, what makes the most sense for us to be to have a reverse (backward) type of schedule, which doesn’t appear to be a thing…yet.
Sub-task 10 of the 13 is our installation task. Everything proceeding this, and the three after, need to be scheduled according to their own durations. For example, the task before it is a milestone invoice that is sent out to the customer. I have the duration set for that one at 60 days so I would like the start date to be that amount of days prior to the installation date. The process continues all the way back to the project ‘start’ date.
For transparency, I have played around with start/end dates but right now the timeline column (of the sub-tasks) is linked to the duration and dependencies columns.
In a perfect world, the installation date would be provided at the form submission and flow down to the sub-tasks to help drive the rest of the dates…and, hopefully, this can all be accomplished through automations/formulas, etc so that the only thing I have to manually set is the dependencies for each new project.
Okay, I apologize, it did get a bit long winded!