How to change how selected columns update 'Progress'?

I use board created from template for ‘Agile Project Management’.
I have column ‘Progress’ which is based on 3 columns: Development, Documentation, Implementation. Each of these columns can have value: ‘Not Started’, ‘No Need’, ‘On Hold’, ‘In Progress’, ‘Done’, ‘Stuck’.
If I select ‘Done’ in any of these columns, this automatically updates column ‘Progress’.
I am looking for a way to update column ‘Progress’ in case I select ‘Not needed’ instead of ‘Done’.

Hi @Oleg - welcome to the community. All you need to do is set “not needed” as an additional “completed” status. On your status column, go into the menu (…) > settings > Customize Status column

image

Then select the additional status you want to be seen as “completed”:

image

This should make the progress bar calculate as expected.

Thanks
Mark

1 Like

Thank you, appreciate your help.

This topic was automatically closed 7 days after the last reply. New replies are no longer allowed.