New Timeline Picker doesn't have Milestone choice

When I opened my boards this morning, I noticed the new Timeline Picker doesn’t have the option to set the chosen date as a milestone anymore. How can I set a date as a milestone now for my Gantt charts?

1 Like

It looks like the new Timeline Picker no longer includes the option to set a milestone directly. I can still see it on my account at the bottom.

However, you can still set a milestone in your Gantt chart by doing the following:

  1. Open your board and navigate to the item where you want to set a milestone.
  2. Go to the Timeline or Date column associated with your Gantt chart.
  3. Set the start and end date to be the same—this will automatically display the item as a milestone in the Gantt view.
  4. Check your Gantt chart to confirm that the milestone appears as a diamond icon.
1 Like

This does not work!

Unfortunately, your directions are inaccurate.


image

Sorry not sure why my version of Monday.com is different, :thinking::pensive:have you tried asking support?

Looks to be that the new timeline column simply does not support the “set as milestone” options

This is no longer working for me either. I am emailing support now.

Support got back to me. You have to go to the Settings for the Timeline column - Customize Timeline - and select Show “Set as Milestone” and it will give you the option on the date picker.

1 Like

You are a hero! Thank you!!! :black_heart: