Hi,
I’d like to use Monday.Com Projects and dependencies to plan ‘right to left’.
The use case is that we have committed to a customer to deliver a project by a certain date and so I need to work backwards to see when we need to start work. So if I want to deliver on 30th November 2025 and my durations total 6 months, I need to start on the 30th of May.
I have a number of tasks, linked ‘Finish to Start’. I want to be able to set a date for the final task, and then have Monday to update the dates for the previous tasks.