1 start date +task durations = end date

Hi All,
I’m trying to add a start date to the first task in my project, then a duration to each task and then have the system work out the end date for me.
Currently my monday.com developer is telling me I have to added a start and end date to every task, this is crazy and doesn’t work for me at all. If something changes I would have to go back and manually change it all again!

This seems like the simplest of requests to me (a layman)
Thanks in advance for your support
C

Hi Charlie,

easy - Insert column “Timeline” - go to column settings and press “Connect with a duartion”.

Now you are able to adjust die timeline only by setting an duration time and an start date(last one only needed if it is not today, because “today” is default).

~ Silas :smiling_face:

1 Like

Having some problems here. I wonder if you have a solution?

Hi Charlie,

add those two automations, it will work bidirectionally, forward/backward:

~ Silas :smiling_face:

2 Likes

This topic was automatically closed 7 days after the last reply. New replies are no longer allowed.