I’m wanting to adjust the timeline start date based on the end date of a dependency and have found online that I could do this with an adjust command in automations, however this option is not available in my own automation recipes nor available to create from scratch - does anyone know how to achieve such an automation?
hi @JennyA
That might be an old article, I don’t believe these automations are available anymore. Instead you can now customize your dependency column and do the setting there. Click the 3-dots menu in the column header and pick Settings > Customize Dependency column.