Hi everyone, running into some issues with setting dates - see needs/ explanation below:
WANTS:
-
Automictically populate a “Start Date” based off of the “Due Date” and a duration (thinking numbers column) within a subitem.
-
Eventually, would like the timeline column to match the start date and due date in the subitem. And for these dates/timeline to automatically adjust as dates or durations change.
Here is a simplified version of our board with explanation. Without these automations, we have to manually adjust start dates and timelines as the due date changes. I may be overcomplicating this - so if easier way please let me know. I tried a formula column but the durations are different for each subitem so it does not work.
-
Overall Due date/start date is there to build dependencies in the subitems to automatically populate the due date based on x amount of dates. This date encompasses the OVERALL start and due date for the task (item)
-
Each subitem is dependent on each other and is its own separate task, so has its own start date and due date as well.
-
Due date needs to stay as deadline mode, but start date does not have to.
-
Each subitem has a different duration and start date.
Thank you!