I am trying to figure out how to workaround the setting that changes the dependency based on weekends. Essentially- the system accounts for weekends and pushes the date to “skip” weekends.
I do need to keep the “work week” setting on, which does not allow items to be scheduled for weekend days
To work around the weekend dependency issue while keeping the “work week” setting enabled, you can try the following approach:
Adjust the Dependency Lag/Lead Time:
In your dependency settings, you can manually adjust the lag or lead time to compensate for the weekend days. For example, if a task is being pushed by two days due to the weekend, set a negative lag (-2 days) to offset it.