How do i automate the status of a subtask to update the progress bar of the item it belongs too?
in this case if i select DONE on status, and its one of 5 subtasks, i’d like it to represent 20% completed on the items progress bar
1 Like
Hi @drew.davies . To get a progress status of subtasks on the parent item you need to click “show summary on parent item” in the property list of the status column of your subtasks. There is no automation necessary for that.
Hi @drew.davies,
@JPinBe was right on target! Here is where you can access this and what you will see as a result:
Hopefully this helps!
Emily
1 Like
This topic was automatically closed 7 days after the last reply. New replies are no longer allowed.