Preface: VERY new Monday user here, experimenting with it for use in a smaller automation company. Familiar with MS Project but not Monday.
I have a normal looking project management board. I am using dependencies to make one task start after another. However if the first task takes too long I want the following task to move along with it. So when I set the status to “done” the completion date is set to “today”.
Now I want one of two things to happen.
- I want the duration to change to reflect the actual duration. I have created a formula to calc the # of days between the start and end dates. However I do not know how to get this into a number format or to push it into the duration column. This way the next task start date will move to the day following the completion date.
OR
- I want the next task’s timeline start date to update to the predecessor’s completion date.
Or am I missing a basic workflow here. If a task goes long and there is a dependent, how do I get the next task to move.
Do most people just change the duration?