I am looking to create an automation that automatically shifts a given timeline when a status is changed.
Let’s say there is a Job that was created and was estimated to take 2 weeks, running from Sept 1 - 14. The Job isn’t started until Sept 6th, and on that day the Status is changed to Work in Progress. I want the timeline to then automatically shift to Sept 6th as the new starting day.
Because each Job is going to have a different estimated timeline, I don’t see a way to use the Set Relative Timeline app as that requires the same duration to be applied to all items.
This would be great to have. I want to push the end date of my planned timelines if the end date has arrived and the status is still not marked as done.