I expect to see a percentage of 40%
8 hours + 8 hours = 16 hours per week
total capacity 40
16/40 = 40%
Why Monday shows me 2%
and 0.37 Hours on 40 Hours (capacity per week)?
Thanks for the detailed context. Based on your description and screenshots (though I can’t see them directly), here’s why Monday.com is likely showing 2% effort instead of your expected 40% in the Workload widget:
Likely Cause: “Effort” Spread Over Task Duration
Monday.com’s Workload widget calculates effort per day, then spreads the total effort across the duration of the task (from Start Date to End Date). So:
If you have:
8 hours total per task
But the task spans multiple days (e.g., 3, 5, or 7 days)
Then Monday.comdivides those 8 hours over the entire duration (It looks like a few months on the timeline?)
Example Breakdown:
Let’s say:
Task 1: 8 hours, Start = July 1, End = July 5 → 5 working days
Task 2: 8 hours, Start = July 1, End = July 5 → 5 working days
Each task gets spread as: 8 hours ÷ 5 days = 1.6 hours/day
Now in a single week, total effort is: 1.6 + 1.6 = 3.2 hours
And Monday compares this to the weekly capacity (40 hours), so: 3.2 / 40 = 8%
If the date range spans longer than a week, even less of the effort falls into a single week. For example, if your task spans 4 weeks, then: 8 hours ÷ 4 weeks = 2 hours/week per task → 2 + 2 = 4 hours/week → 4 / 40 = 10%
This could explain your 2% if the task spans more time.