Hi! My workflow starts by creating an item, updating the progress status, and then creating subitems under the main item. Is there a way to set the start date or due date to today?
Hi @Carla22
You could just use a creation log field and call it Start date and change the settings on the field to just date
That way every time you create a subitem it will set the date to today as it uses the date you created the subitem
Another way is to use an automation, when you change the status on the parent item set the subitem date to current date + 0 days

Hope this provides what you need
many thanks in advance
Dan
1 Like
It worked! Thank you so much for your help!