Hello community,
Using the Workload widget in a dashboard allows me to see if some of my team members are over-allocated in a given time period. But that is based on assigned tasks in the respective project boards.
I’ve been trying to find a way, though, to visualize workload based on maximum time allocations at the project level. For example. Alice is working on three projects, and each individual project board has a Workload widget that specifies her capacity for that project, let’s say 4, 8, and 16 hours weekly respectively. I want my dashboard Workload widget to combine those capacity numbers and give me that 28-hour number against a total weekly capacity of 40. Is this possible? Or, is there another way to see this?