My use case is that I know the work items coming for the quarter, the effort required and the resources I have available. Currently I have a googlesheet which then collates by week or month the level of demand and the level of resource and highlights gaps or excesses, so was hoping to recreate in Monday.
It looks like a capacity planner could do the latter part, but neither resource planner nor cap manager would reflect the tasks and effort required, unless I fully recreate the effort information in some way at an assignee level in the resource planner (despite it being connected to the project)?
If I’m missing something fundamental please let me know. Likewise if its a real limitation and I’ll just stick with my googlesheet.